Fixed
Pot Hole #3
Reported via iOS in the Potholes / Highway Condition category anonymously at 23:36, Wed 19 June 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6130519.
This pot hole has been logged 3 times now. I have therefore taken the time to measure the depth which is approx 45mm to 50mm as per the photo.
Please fix rather than just close without providing a valid reason.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 23:36, Wed 19 June 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that the carriageway defects meet the investigatory level for repairs and work has been scheduled to resolve them. This should be completed within a 6 month time frame and please be assured that you will receive an update once repairs are concluded.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 13:36, Fri 21 June 2024
-
Still open, via questionnaire, 05:57, Thu 18 July 2024
-
Still open, via questionnaire, 12:23, Thu 15 August 2024
-
Still open, via questionnaire, 17:47, Thu 12 September 2024
-
Still open, via questionnaire, 21:57, Fri 11 October 2024
-
Come on WNC. This is a main route. Please sort.
Posted anonymously at 21:46, Tue 15 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on FMS-6130519-1 and add updates. The expected completion date for these works will be 19/12/2024.
Posted by West Northamptonshire Council at 07:23, Wed 16 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 08:51, Wed 30 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 10:48, Fri 1 November 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 11:53, Fri 1 November 2024
This report is now closed to updates from the public. You can make a new report in the same location.