Fixed
The pavement for the entire cul de sac is uneven and dangerous for the elderly and wheelchair user.
Reported via mobile in the Pothole / Failed Reinstatement category anonymously at 14:57, Mon 1 July 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6177372.
The pavement is in a dangerous state particularly for the elderly and wheelchair user. It is generally in a bad state but at the top of the cul de sac the refuse collection vans are partially responsible for the damage/dips due to the way they drive on the pavement. The turning point at the top of the cul de sac is too small for the heavy Veolia lorries and they mount the pavement. The council have told them to reverse into High View but frequently they don’t! I hope they and not the taxpayer pick up some of the tab for the damage they have caused!
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 14:57, Mon 1 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that the footpath will be repaired within the next 28 days. in regard to the carriageway there are currently no defects that meet our investigatory criteria for repair. These levels have been agreed with West Northamptonshire Council. We will continue to monitor the defect via our routine highway safety inspections.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 15:58, Mon 8 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 08:14, Thu 11 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 13:39, Thu 11 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 14:01, Thu 11 July 2024
This report is now closed to updates from the public. You can make a new report in the same location.