In progress
The road side sink is totally blocked with earth and grass.
Reported via mobile in the Blocked/Damaged category anonymously at 10:51, Fri 5 July 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6194360.
I have previously reported many drains in our area which are not draining surface water away. This sink outside of my property 195 Main Road is now totally blocked with earth and grass. This has been getting worse for at least 2 months.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 10:51, Fri 5 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that the carriageway defects meet the investigatory level for repairs and work has been scheduled to resolve them. This should be completed within a 6 month time frame and please be assured that you will receive an update once repairs are concluded.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 11:07, Thu 11 July 2024
-
No change as yet and the sink is still blocked. Could take up to 6 months to rectify...really ?
Posted anonymously at 13:23, Wed 17 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that the carriageway defects do not pose any immediate flood risks. This is why we have placed this on a 6 month ticket. However, we hope to complete this as soon as possible.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 13:36, Fri 19 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 07:18, Fri 16 August 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 10:54, Fri 16 August 2024
Provide an update