Weeds on bike path
Reported via Android in the Weeds category by Monica de Bokx at 09:48, Fri 12 July 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6221177.
The weeds are making this bike path unfit for purpose. Can they be removed please? At the top of the path there is a bit of wired fencing sticking out causing a bit of a hazard to any unknowing cyclist or pedestrian coming around that corner. Can that be removed or repaired please?
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 09:48, Fri 12 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 3.2 days.
Posted by West Northamptonshire Council at 11:46, Fri 19 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 07:26, Fri 26 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 11:10, Fri 26 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 12:20, Fri 26 July 2024
This report is now closed to updates from the public. You can make a new report in the same location.