Path very uneven
Reported via desktop in the Pothole / Failed Reinstatement category anonymously at 10:43, Mon 22 July 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6259316.
This path has been neglected for years. My mother in law walks with a frame and has difficulty getting along the path. She is 86 and could fall.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 10:44, Mon 22 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 37.3 days.
Posted by West Northamptonshire Council at 11:10, Mon 29 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 13:48, Fri 16 August 2024
-
Still open, via questionnaire, 11:11, Mon 19 August 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 10:49, Tue 27 August 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 11:58, Wed 28 August 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 09:35, Tue 3 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 10:02, Wed 4 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 09:33, Thu 5 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 08:22, Fri 6 September 2024
This report is now closed to updates from the public. You can make a new report in the same location.