Cannot fully access the bridleway due to thick ground vegetation and overgrown hedgerows.
Reported via mobile in the Passage-Obstructed/Overgrown category anonymously at 11:21, Mon 22 July 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6259591.
I tried to ride this bridleway last week and was unable to fully access the whole bridleway as I got so far and had to turn back. This was due to dense ground cover which was very long and hard to navigate and also due to overgrown hedges and thorns blocking the way.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 11:21, Mon 22 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the vegetation meets the criteria for a Priority 4 response. We will schedule vegetation clearance to be completed within 26 weeks. Our current average response time for a Priority 4 is 37.3 days.
Posted by West Northamptonshire Council at 09:10, Thu 25 July 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 06:17, Sunday 19 January 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 09:07, Monday 20 January 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 11:37, Tuesday 21 January 2025
This report is now closed to updates from the public. You can make a new report in the same location.