Fixed
Overgrown Trees
Reported via iOS in the Restricted Visibility / Overgrown / Overhanging category anonymously at 21:07, Thu 8 August 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6334046.
One day a cyclist will run a child walking to Millway school over simply because the child cannot walk on the footpath side of the cycle path. - Please resolve.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 21:07, Thu 8 August 2024
-
Investigation: Ongoing - We are currently waiting for a greens report.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 12:53, Fri 9 August 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 38.9 days.
Posted by West Northamptonshire Council at 13:09, Mon 12 August 2024
-
Still open, via questionnaire, 21:33, Thu 5 September 2024
-
Still open, via questionnaire, 07:35, Fri 4 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on FMS-6334046 and add updates. The expected completion date for these works will be 10/02/2025 .
Posted by West Northamptonshire Council at 07:13, Mon 14 October 2024
-
Hi WNC,
You stated that this is a P4 ticket on 12/08/24 which you said the average response time is 38 days.
We are well past that. Please prioritise this!!
Thanks.
Posted anonymously at 21:36, Tue 15 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 2 repair. We will schedule a repair to be completed within 7 days.
Posted by West Northamptonshire Council at 07:20, Wed 16 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Duplicate
State changed to: Duplicate
Posted by West Northamptonshire Council at 15:22, Tue 5 November 2024
-
Questionnaire filled in by problem reporter
State changed to: Fixed
Posted anonymously at 22:56, Tue 5 November 2024
-
Investigation: Completed (Work Completed), Defect Repair: Duplicate - Thank you for your enquiry. Works were completed on 18/10/2024.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysState changed to: Duplicate
Posted by West Northamptonshire Council at 10:21, Wed 6 November 2024
-
Investigation: Completed (Work Completed), Defect Repair: Duplicate
State changed to: In progress
Posted by West Northamptonshire Council at 06:26, Sunday 19 January 2025
-
Investigation: Completed (Work Completed), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 09:11, Monday 20 January 2025
This report is now closed to updates from the public. You can make a new report in the same location.