Raised road surface , approximately 80cm diameter x 9cm high .

Reported via desktop in the Potholes / Highway Condition category anonymously at 14:15, Tue 3 September 2024

Sent to West Northamptonshire Council less than a minute later. ref: 6431359.

On the approach to Gt Oxendon from Mkt Harborough about 50 metres before the Church there is quite a large hump / bulge in the centre of the carriageway , it measures approximately 80cm in diameter x 9cm in height and is domed in shape. I was unfortunate to hit this hump in the centre of road whilst riding my motorcycle which then sent me across to the opposite side of the road, luckily there was no oncoming traffic otherwise I might not be sending this report. As can be seen in the photo's it appears that I am not the only road user to have found this defect in the road surface as gouges can be seen in the surface.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 14:15, Tue 3 September 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the photo/s and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 38.9 days.

    Posted by West Northamptonshire Council at 15:28, Tue 3 September 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 08:39, Thu 24 October 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by West Northamptonshire Council at 08:16, Fri 6 December 2024

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 06:11, Mon 9 December 2024

This report is now closed to updates from the public. You can make a new report in the same location.