Blocked drain on Boughton roundabout A428

Reported via desktop in the Blocked/Damaged category anonymously at 09:20, Sun 8 September 2024

Sent to West Northamptonshire Council less than a minute later. ref: 6448393.

North west corner

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 09:21, Sun 8 September 2024

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the photo/s and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 38 days.

    Posted by West Northamptonshire Council at 11:35, Mon 9 September 2024

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 19:01, Sat 21 September 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by West Northamptonshire Council at 08:48, Thu 26 September 2024

  • Questionnaire filled in by problem reporter

    State changed to: Fixed

    Posted anonymously at 10:36, Sun 3 November 2024

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing - Thank you for your enquiry. A qualified Highways Inspector has assessed the photo/s and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 38 days.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    State changed to: In progress

    Posted by West Northamptonshire Council at 09:35, Tue 12 November 2024

Provide an update

Your information will only be used in accordance with our privacy policy

Next: Tell us about you

Your update

Tell us about you

Do you have a West Northamptonshire Council FixMyStreet password?