Fixed
Drain in front of Lunchfield Lodge on Lunchfield Lane cannot take all the rain and it comes bubbling up
Reported via desktop in the Blocked/Damaged category anonymously at 14:12, Monday 9 September 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6453277.
The drain on street in front of the house bubbles up and does not drain away. There are manholes in the property behind called Chapel House that also take away rain water and they cannot manage it and the water bubbles up and floods the rear of his property. It floods his patio by 6" The water is rain water, not sewage that passes through the drain under the lawn of Chapel House.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 14:12, Monday 9 September 2024
-
Since I moved to this house the patio and and garage flood at least a couple of times a year. The problem is the drainage cannot handle the water volume when it rains heavily and so it backs up through the drains in the street and on the lawn of the care home next door. The lawn of the care home becomes sodden and pours through the fence separating our properties and floods my patio area and my garage. This happened again on Saturday night and was the 3rd time this year. As you can see from the water level is very high (about 6”) on the garage wall flooding the patio and the garage floor causing damage to possessions inside. Other than the inconvenience of cleaning up the mess every time this happens I am concerned about the damage being done to my garage.
Posted anonymously at 14:25, Monday 9 September 2024
-
Investigation: Completed (Highways to Monitor, Routine Inspection Programme) - Thank you for your enquiry. A qualified Highways Inspector has assessed the location, and we can confirm that in accordance with the WNC Highways Inspection Manual, this defect does not meet the investigatory levels for a repair. We will continue to monitor the condition as part of our routine highway inspection schedule. Should you notice the defect worsening, please inform us by raising a new Fixmystreet enquiry.
State changed to: Closed
Posted by West Northamptonshire Council at 14:09, Tuesday 10 September 2024
-
Investigation: Ongoing (Highways to Monitor, Routine Inspection Programme) - Thank you for your enquiry. A qualified Highways Inspector has assessed the location, and we can confirm that in accordance with the WNC Highways Inspection Manual, this defect does not meet the investigatory levels for a repair. We will continue to monitor the condition as part of our routine highway inspection schedule. Should you notice the defect worsening, please inform us by raising a new Fixmystreet enquiry.
State changed to: Investigating
Posted by West Northamptonshire Council at 10:18, Wednesday 11 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 13 days.
Posted by West Northamptonshire Council at 10:28, Wednesday 11 September 2024
-
This is one of the manholes in our neighbours garden (Chappell house) that floods and pours through our fence.
Posted anonymously at 14:08, Wednesday 11 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 13 days.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 15:59, Wednesday 11 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 18:59, Saturday 21 September 2024
-
Since I last complained of this problem we have been flooded twice more. We were up until 02.00 this morning cleaning up the damage again! The care home next door has a garden that turns into a lake when the manholes start spewing water. Their drainpipe also empties directly onto the path all of which ends up against my fence and along with the drain in front of our garage floods my patio and garage. My neighbours have the same issue and this needs sorting immediately.
Posted anonymously at 13:35, Tuesday 24 September 2024
-
Investigation: Not Started (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 08:12, Thursday 26 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 13 days. This will be completed by the 09/10/2024.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 08:55, Wednesday 2 October 2024
-
Please can you let me know what is happening. My neighbours and I are extremely worried that we will be flooded again. The last report said the repair was located and would be repaired by the 11th October. Was this done?
Posted anonymously at 09:01, Tuesday 19 November 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 13 days. This will be completed by the 09/10/2024.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 15:34, Tuesday 26 November 2024
-
Please let me know what is happening. There doesn't seem to have been anything done yet and someone from the council came last week and told us they haven't even looked at it yet!! The work was supposed to have been completed in October!
Posted anonymously at 16:46, Tuesday 26 November 2024
-
Investigation: Not Started (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 12:31, Monday 2 December 2024
-
Investigation: Completed (Work Completed), Defect Repair: Work Completed - Thank you for your enquiry. We can confirm that works have been completed on the 02/12/2024.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 15:45, Monday 2 December 2024
This report is now closed to updates from the public. You can make a new report in the same location.