Investigating
Drain blocked
Reported via mobile in the Blocked/Damaged category anonymously at 10:50, Sunday 22 September 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6499176.
Drain blocked.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 10:50, Sunday 22 September 2024
-
Investigation: Ongoing - Thank you for your enquiry. West Northants received approximately 140mm of rain over a short period of time, resulting in severe flash flooding in many areas. The heavy rainfall had the ability to overwhelm the surface water drainage system. If your report is a repeat flooding incident, please could update this enquiry with further information, so that we can investigate. If this is not a repeat incident, we will close the enquiry after 7 days and the highways team will continue to monitor the location
Posted by West Northamptonshire Council at 13:17, Wednesday 25 September 2024
-
Drain still blocked 16/10 long after the heavy rainfall. Causing lorries to splash walkers on the footpath and cars to take the corner on the wrong side of the road!!
Posted anonymously at 13:25, Wednesday 16 October 2024
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by West Northamptonshire Council at 13:26, Wednesday 16 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the flooding has been assessed and requires a Priority 4 response. We will schedule drainage investigation work to be completed within 26 weeks. When the investigation has been completed, we will inform you of our findings and course of action. Our current average response time for a Priority 4 is 38 days.
Posted by West Northamptonshire Council at 09:23, Monday 21 October 2024
-
Flooded again after now - now icing over causing cars to skid!!
Posted anonymously at 08:31, Tuesday 19 November 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue and a works order has been raised on a routine safety inspection. The expected completion date for these works will be 20/11/24
Posted by West Northamptonshire Council at 11:15, Friday 22 November 2024