Fixed
Drain blocked
Reported via iOS in the Blocked/Damaged category anonymously at 12:45, Sun 22 September 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6499594.
Drain is blocked. Water shedding from previous blocked drain (also reported today) is overflowing here and going further down the road. In todays heavy rain that water flowed all the way to the bottom of the road and onto driveways
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 12:46, Sun 22 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the flooding has been assessed and requires a Priority 3 response. We will schedule drainage investigation work to be completed within 28 days. When the investigation has been completed, we will inform you of our findings and course of action. Our current average response time for a Priority 3 is 13 days.
Posted by West Northamptonshire Council at 08:49, Mon 23 September 2024
-
I may have ticked Fixed by mistake when I reported this earlier. Can I clarify that none of the drains have been fixed and with the additional rain the problem is getting worse with a significant risk of water getting into properties.
This is an ongoing & worsening problem. We have mentioned to crews that have been out before that the drains further up Brook Court are blocked and are adding to the problem. No work has been done on these. Just to clarify again - none of the drains on Brook Coury have been fixed.
Posted by Vyv Hogg at 14:54, Mon 23 September 2024
-
Investigation: Ongoing (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. West Northants received approximately 140mm of rain over a short period of time, resulting in severe flash flooding in many areas. The heavy rainfall had the ability to overwhelm the surface water drainage system. If your report is a repeat flooding incident, please could update this enquiry with further information, so that we can investigate. If this is not a repeat incident, we will close the enquiry after 7 days and the highways team will continue to monitor the location
Posted by West Northamptonshire Council at 13:16, Wed 25 September 2024
-
Reporting this as a repeat issue. Please investigate, and resolve, do not delete.
Posted anonymously at 19:43, Wed 25 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the photo/s and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 13 days.
Posted by West Northamptonshire Council at 12:11, Mon 30 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 14:13, Thu 10 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 08:54, Mon 14 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 12:06, Mon 11 November 2024
This report is now closed to updates from the public. You can make a new report in the same location.