Fixed
Drain overflowed and shed water into property
Reported via iOS in the Blocked/Damaged category anonymously at 12:51, Sun 22 September 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6499619.
This drain repeatedly fails to carry water away. And with the 2 drains up the street (already reported today) also blocked this drain ends up overwhelmed. This drain is clearly not big enough to cope with the water it needs to manage and needs improving
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 12:51, Sun 22 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the flooding has been assessed and requires a Priority 3 response. We will schedule drainage investigation work to be completed within 28 days. When the investigation has been completed, we will inform you of our findings and course of action. Our current average response time for a Priority 3 is 13 days.
Posted by West Northamptonshire Council at 08:49, Mon 23 September 2024
-
Reporting this as a repeat issue. Please investigate, and resolve, do not delete.
Posted anonymously at 19:43, Wed 25 September 2024
-
Drain unable to cope with the water again under light rain when we are anticipating heavy rain overnight according to weather updates. You can see the water running down the road to this grid which constantly becomes overwhelmed. This has occurred many times and although the drain has been cleared through historically it is unable to cope with heavier rain water and is an ongoing issue that requires a long term fix.
Posted anonymously at 18:09, Thu 26 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the flooding has been assessed and requires a Priority 3 response. We will schedule drainage investigation work to be completed within 28 days. When the investigation has been completed, we will inform you of our findings and course of action. Our current average response time for a Priority 3 is 13 days.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 08:53, Wed 2 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 14:13, Thu 10 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 08:53, Mon 14 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 10:30, Fri 18 October 2024
This report is now closed to updates from the public. You can make a new report in the same location.