Reported via iOS in the Blocked/Damaged category anonymously at 16:23, Monday 23 September 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6505763.
Another overflowing drain to be cleared out please
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 16:23, Monday 23 September 2024
-
Investigation: Ongoing - Thank you for your enquiry. West Northants received approximately 140mm of rain over a short period of time, resulting in severe flash flooding in many areas. The heavy rainfall had the ability to overwhelm the surface water drainage system. If your report is a repeat flooding incident, please could update this enquiry with further information, so that we can investigate. If this is not a repeat incident, we will close the enquiry after 7 days and the highways team will continue to monitor the location
Posted by West Northamptonshire Council at 13:04, Wednesday 25 September 2024
-
Reporting this as a repeat issue. Please investigate, and resolve, do not delete.
Posted anonymously at 19:42, Wednesday 25 September 2024
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by West Northamptonshire Council at 19:42, Wednesday 25 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the photo/s and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 38 days.
Posted by West Northamptonshire Council at 10:38, Friday 27 September 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 13:10, Friday 22 November 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 12:26, Thursday 28 November 2024
Provide an update