In progress
Blocked drain
Reported via mobile in the Blocked/Damaged category anonymously at 16:01, Wed 16 October 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6623391.
This drain has been in this state for months. It only recently came to our notice, after the heavy rain a couple of weeks ago, when the amount of water that fell, just had no where to go and it ended in the property on the opposite side of the road, No 6 Kerrfield. This was attended by an Environmental Agency member on the night of the downpour, outside No.10 a and b, at around 11pm. No action has been taken since.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 16:01, Wed 16 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the flooding has been assessed and requires a Priority 4 response. We will schedule drainage investigation work to be completed within 26 weeks. When the investigation has been completed, we will inform you of our findings and course of action. Our current average response time for a Priority 4 is 38 days.
Posted by West Northamptonshire Council at 08:27, Wed 23 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 11:57, Fri 15 November 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 12:41, Mon 25 November 2024
Provide an update