Fixed
Missing Reflectors on new Central Reservation Bollards
Reported via desktop in the Safety Bollard - Damaged/Missing category anonymously at 09:38, Wed 23 October 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6648355.
There are 2 new central reservation bollards opposite the new entrance of the Bellway Housing development. The bollards have reflectors on the front face but not on the rear side. These bollards are on raised kerbed island are not visible at night and are very dangerous as can't be seen if someone has to drive into the middle of the road around an obstacle. Looking at all similar bollards in Daventry there are reflectors on the rear face. These needs to be changed before there is a serious accident.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 09:38, Wed 23 October 2024
-
Investigation: Completed (No Action Necessary) - Thank you for your enquiry. A qualified Highways Inspector has assessed the location, and we can confirm that in accordance with the WNC Highways Inspection Manual, this defect does not meet the investigatory levels for a repair. We will continue to monitor the condition as part of our routine highway inspection schedule. Should you notice the defect worsening, please inform us by raising a new Fixmystreet enquiry.
State changed to: No further action
Posted by West Northamptonshire Council at 12:13, Tue 29 October 2024
-
Investigation: Ongoing (No Action Necessary), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the photo/s and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 62 days.
State changed to: Investigating
Posted by West Northamptonshire Council at 09:01, Mon 2 December 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the photo/s and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 16 days.
Posted by West Northamptonshire Council at 09:07, Mon 2 December 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 08:43, Thu 5 December 2024
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 12:52, Tue 10 December 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 08:08, Wed 11 December 2024
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: In progress
Posted by West Northamptonshire Council at 07:54, Wednesday 8 January 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 17:33, Wednesday 8 January 2025
This report is now closed to updates from the public. You can make a new report in the same location.