In progress
Blocked drain at top of Brampton Lane
Reported via desktop in the Blocked/Damaged category anonymously at 18:48, Fri 25 October 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6659493.
By the A508 roundabout
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 18:48, Fri 25 October 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 38 days.
Posted by West Northamptonshire Council at 08:52, Mon 28 October 2024
-
Still open, via questionnaire, 19:02, Fri 22 November 2024
-
Still open, via questionnaire, 23:13, Fri 20 December 2024
-
Still open, via questionnaire, 08:30, Saturday 18 January 2025
-
Still open, via questionnaire, 09:02, Saturday 15 February 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 11:09, Thursday 13 March 2025
-
Still open, via questionnaire, 10:14, Saturday 15 March 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 08:35, Tuesday
Provide an update