Fixed
Massive pot holes and thick mud
Reported via mobile in the Potholes / Highway Condition category anonymously at 12:47, Wed 4 December 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6818533.
Massive pot holes been there for ages and getting worse all along the road, and the mud is extremely dangerous and slippy
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 12:47, Wed 4 December 2024
-
Investigation: Completed (Defect Found) - Thank you for your enquiry. A Community Steward has assessed the location and we can confirm that the defect meets the requirement for a Priority 1 we will schedule a road sweeper to attend this location within 24hrs should be by the end of today 5/12/24
Posted by West Northamptonshire Council at 10:24, Thu 5 December 2024
-
The potholes have still not been fixed. The whole road to Brackley is riddled with potholes causing traffic to swerve to avoid them. Potholes seem to be patched one at a time even if they are part of a group.The whole road needs re-surfacing before it fails. It was last properly attended to 30 years ago
Posted anonymously at 09:32, Saturday 8 March 2025
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by West Northamptonshire Council at 09:33, Saturday 8 March 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 18.5 days.
Posted by West Northamptonshire Council at 11:01, Monday 10 March 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 09:54, Thursday 13 March 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 11:38, Monday 17 March 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 13:57, Monday 17 March 2025
This report is now closed to updates from the public. You can make a new report in the same location.