Action scheduled
300mm hole 50+mm deep
Reported via mobile in the Potholes / Highway Condition category anonymously at 18:35, Mon 23 December 2024
Sent to West Northamptonshire Council less than a minute later. ref: 6894666.
Existing repairs of this pothole that burst many tyres is crumbling and coming out. Revealing the original deep sharp edged hole that was filled. Not very well.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 18:35, Mon 23 December 2024
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A Community Steward has assessed the location and we can confirm that the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 62 days.
Posted by West Northamptonshire Council at 08:29, Tue 24 December 2024
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 09:03, Friday 7 February 2025
-
Issue has just ruined my tyre.
Posted anonymously at 19:52, Thursday 13 February 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 2 repair. We will schedule a repair to be completed within 7 days.
Posted by West Northamptonshire Council at 12:23, Friday 14 February 2025
Provide an update