Investigating
Potholes reopened again more!
Reported via mobile in the Potholes / Highway Condition category anonymously at 08:53, Wednesday 8 January 2025
Sent to West Northamptonshire Council less than a minute later. ref: 6948854.
The lane has recently been repaired but I’m afraid the pothole fixed has somewhat failed and an even larger area around it has disintegrated in the recent inclement weather.
Please can this be fixed as soon as possible as vehicles are swerving around it and this space is very dangerous. Thank you
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 08:54, Wednesday 8 January 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 62 days.
Posted by West Northamptonshire Council at 11:26, Thursday 9 January 2025
-
This pothole is now far worse. If it is not fixed soon there will be a serious accident as cars and lorries are having to swerve to avoid it.
Posted anonymously at 09:16, Monday 13 January 2025
-
Investigation: Completed (Duplicate), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue and a works order has been raised on a routine safety inspection. The expected completion date for these works will be 10/07/2025 hopefully sooner.
Posted by West Northamptonshire Council at 22:23, Tuesday 14 January 2025
-
The problem is getting worse daily and further potholes are creeping across the mill lane. There is a drainage issue somewhere in the vicinity that is believed to be causing the continuing damage. There is a huge concern over safety of drivers and pedestrians alike but also a further concern the road will become impassable. A July fix, as is the latest estimation will be way too late. It needs immediate attention.
Posted anonymously at 09:10, Wednesday
Still open, via questionnaire -
Investigation: Completed (Duplicate), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue and a works order has been raised on a routine safety inspection. The expected completion date for these works will be 10/07/2025 hopefully sooner.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 18:47, Wednesday
Provide an update
Your information will only be used in accordance with our privacy policy