In progress
Many huge potholes bigger than ten inches mainly on previous repairs
Reported via mobile in the Potholes / Highway Condition category by Andrea Brown at 18:48, Sunday 12 January 2025
Sent to West Northamptonshire Council less than a minute later. ref: 6969559.
This is just a 400 yd stretch there is at least another 400 yards towards Daventry Rd Kilsby
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 18:48, Sunday 12 January 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the photo/s and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 62 days.
Posted by West Northamptonshire Council at 13:40, Thursday 16 January 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 10:53, Friday 24 January 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 11:03, Tuesday