Pothole - large

Reported via desktop in the Potholes / Highway Condition category anonymously at 15:20, Friday 24 January 2025

Sent to West Northamptonshire Council less than a minute later. ref: 7028146.

On the approach to the roundabout junction from PAN to Kettering Road, there is a large pot hole as the lane splits into two

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 15:21, Friday 24 January 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 73 days.

    Posted by West Northamptonshire Council at 11:58, Monday 27 January 2025

  • Getting bigger

    Posted anonymously at 12:14, Tuesday 18 February 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue and a works order has been raised on a routine safety inspection. The expected completion date for these works will be 28/07/2025.

    Posted by West Northamptonshire Council at 08:25, Wednesday 19 February 2025

  • This needs to be repaired as a matter of urgency. Please respect before it causes serious damage

    Posted anonymously at 17:04, Tuesday 4 March 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue and a works order has been raised on a routine safety inspection. The expected completion date for these works will be 28/07/2025.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by West Northamptonshire Council at 13:20, Wednesday 5 March 2025

  • This needs an urgent repair now, not in 4 months time. It is in the middle of the carriageway and almost unavoidable. You have wasted money resurfacing a nearby stretch of this road which ironically had zero issues with it yet you cannot do an emergency repair of this pothole?

    Posted anonymously at 14:18, Wednesday 5 March 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue and a works order has been raised on a routine safety inspection. The expected completion date for these works will be 28/07/2025.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by West Northamptonshire Council at 14:52, Wednesday 5 March 2025

  • I don’t think this repair timescale is in line with the road standards policy set by the council based on its size (width and depth). It needs re inspection and a faster repair - you have equipment on park Avenue this week.

    Posted anonymously at 15:13, Wednesday 5 March 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue and a works order has been raised on a routine safety inspection. The expected completion date for these works will be 28/07/2025.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by West Northamptonshire Council at 16:36, Wednesday 5 March 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 10:20, Thursday 13 March 2025

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by West Northamptonshire Council at 10:34, Thursday 20 March 2025

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 11:00, Thursday 20 March 2025

This report is now closed to updates from the public. You can make a new report in the same location.