Fixed
4/5 potholes on junction
Reported via desktop in the Potholes / Highway Condition category anonymously at 13:56, Saturday 8 February 2025
Sent to West Northamptonshire Council less than a minute later. ref: 7104712.
On the t-junction where you exit Brafield Road and join the Newport Pagnell Road. These have been bodged filled before and holes now reappeared again
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 13:56, Saturday 8 February 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 18.5 days.
Posted by West Northamptonshire Council at 09:12, Tuesday 11 February 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 09:09, Thursday 20 February 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 08:37, Tuesday 25 February 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 06:53, Thursday 27 February 2025
This report is now closed to updates from the public. You can make a new report in the same location.