Fixed
Several potholes either side of traffic calming scheme
Reported via desktop in the Potholes / Highway Condition category anonymously at 09:16, Thursday 13 March 2025
Sent to West Northamptonshire Council less than a minute later. ref: 7271143.
Potholes growing not receiving attention
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 09:17, Thursday 13 March 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 55.5 days.
Posted by West Northamptonshire Council at 12:51, Thursday 13 March 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 10:58, Wednesday 9 April 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 11:45, Friday 25 April 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 09:17, Wednesday 30 April 2025
This report is now closed to updates from the public. You can make a new report in the same location.