Fixed
Blocked drain by the Green
Reported via desktop in the Blocked/Damaged category anonymously at 13:31, Thursday 13 March 2025
Sent to West Northamptonshire Council less than a minute later. ref: 7273024.
Looks like a vehicle has driven up onto the verge and caused earth and mud to fall down and block the drain.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 13:32, Thursday 13 March 2025
-
Investigation: Completed (Defect Found) - Thank you for your recent enquiry, our Highways Inspector has visited the site and was unable to identify any flooding at the time of the visit. An initial drainage investigation has been raised and will be undertaken within 28 days.
Posted by West Northamptonshire Council at 07:04, Tuesday 18 March 2025
-
Still open, via questionnaire, 12:20, Friday 11 April 2025
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by West Northamptonshire Council at 10:22, Sunday 25 May 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the flooding has been assessed and requires a Priority 3 response. We will schedule drainage investigation work to be completed within 28 days. When the investigation has been completed, we will inform you of our findings and course of action. Our current average response time for a Priority 3 is 13 days.
Posted by West Northamptonshire Council at 15:47, Monday 2 June 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 09:02, Friday 25 July 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 10:25, Thursday 31 July 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 10:43, Monday 4 August 2025
This report is now closed to updates from the public. You can make a new report in the same location.