Fixed
Frame to services cover is not flush with footpath
Reported via mobile in the Pothole / Failed Reinstatement category anonymously at 17:03, Wed 14 May 2025
Sent to West Northamptonshire Council less than a minute later. ref: 7569845.
The services access is protruding above the pavement presenting a trip hazard. Location is in line with no.61 Meadow View.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 17:03, Wed 14 May 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 47 days.
Posted by West Northamptonshire Council at 14:32, Fri 16 May 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 11:18, Mon 1 September 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 09:11, Wed 3 September 2025
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 11:07, Wed 3 September 2025
This report is now closed to updates from the public. You can make a new report in the same location.