Large pot hole going up the hill

Reported via mobile in the Potholes / Highway Condition category anonymously at 15:13, Wed 16 July 2025

Sent to West Northamptonshire Council less than a minute later. ref: 7887709.

Issue was reported and a report came back to say it had been fixed: it hasn’t

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 15:13, Wed 16 July 2025

  • Investigation: Ongoing - Thank you for your enquiry. Our inspector has attended the pinned location but unfortunately was unable to locate the defect. Please could you confirm the location and if possible the what3words or alternatively, if safe to do so a photo of the surrounding area.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by West Northamptonshire Council at 09:00, Thu 17 July 2025

  • The pot hole is immediately as you turn left up the hill on this road. It’s unmissable. It’s on the left hand side of the road as you go up the hill

    Posted anonymously at 10:12, Thu 17 July 2025

  • Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    Posted by West Northamptonshire Council at 10:13, Thu 17 July 2025

  • Apologies this has been highlighted in the wrong area.

    Posted anonymously at 11:47, Thu 17 July 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 52 days.

    Posted by West Northamptonshire Council at 07:56, Wed 23 July 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 09:21, Mon 13 October 2025

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by West Northamptonshire Council at 08:02, Monday 19 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 14:53, Tuesday 20 January 2026

This report is now closed to updates from the public. You can make a new report in the same location.