Pot Hole

Reported via desktop in the Potholes / Highway Condition category by Harry Minns at 12:24, Sat 27 September 2025

Sent to West Northamptonshire Council less than a minute later. ref: 8221512.

3 Inch Deep 7 Inch Wide 9 Inch Long

Parish Code WH026

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 12:25, Sat 27 September 2025

  • Investigation: Completed (Defect Found) - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.

    Posted by West Northamptonshire Council at 14:26, Tue 30 September 2025

  • Investigation: Ongoing (Defect Found) - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.

    Posted by West Northamptonshire Council at 07:37, Thu 20 November 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.

    Posted by West Northamptonshire Council at 18:05, Thu 27 November 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 13:39, Wed 17 December 2025

  • Investigation: Completed (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by West Northamptonshire Council at 09:36, Mon 22 December 2025

  • Investigation: Completed (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 13:42, Tue 23 December 2025

This report is now closed to updates from the public. You can make a new report in the same location.