In progress
Several large, deep, sharp-edged potholes
Reported via desktop in the Potholes / Highway Condition category anonymously at 08:16, Fri 3 October 2025
Sent to West Northamptonshire Council less than a minute later. ref: 8246526.
Several large, deep, sharp-edged potholes
The road surface on the stretch of road from the Abthorpe crossroads to Silverstone are and have been appalling for years. The conditions continue to worsen, not helped by large volumes of traffic diverting from the A43.
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 08:16, Fri 3 October 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A Community Steward has assessed the location and we can confirm that the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 12 days.
Posted by West Northamptonshire Council at 11:11, Fri 3 October 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 09:07, Mon 13 October 2025
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 11:38, Fri 17 October 2025
-
Investigation: Completed (Defect Found), Defect Repair: Temporary Repair Completed - A permanent repair will be carried out in the next 28 days.
Posted by West Northamptonshire Council at 12:22, Fri 17 October 2025
-
This whole stretch of road has multiple potholes. Some are so big they will damage someone's car/tyres! There is a sign up that the road was closed for a few days on the 21st November; however, there is no sign of any potholes being attended to. With the increase in vehicles using the road due to the A43 road works, these potholes need attending to ASAP.
Posted anonymously at 13:30, Thu 27 November 2025
-
Investigation: Completed (Duplicate), Defect Repair: Temporary Repair Completed - A permanent repair will be carried out in the next 28 days. - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on 7870215 and add updates. The expected completion date for these works will be on or before 30/1/26
Posted by West Northamptonshire Council at 13:01, Fri 28 November 2025
Provide an update
Your information will only be used in accordance with our privacy policy