In progress
Pothole just after roundabout
Reported via mobile in the Potholes / Highway Condition category anonymously at 13:43, Fri 5 December 2025
Sent to West Northamptonshire Council less than a minute later. ref: 8506421.
There's a pothole that sits away from the curb in your line of driving so difficult to avoid, particularly in dark. Has cause damage to tyre of my car. Needs to be reviewed to prevent potential damage to someone else's car
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 13:43, Fri 5 December 2025
-
I am writing to you regarding the terrible state of the roads in and around daventry. i have just had two new front tyres on my car due to bulges caused by pot holes. two days later, whilst driving around a roundabout, i have hit yet another deep pot hole which has now caused another bulge. this has now cost me nearly £800 due to the conditions of the roads in my local town. i had no other choice but to drive through the pot hole as another car was driving on the inside of me, i had nowhere else to go! the other pot holes happened when it was dark which meant they weren’t visible on the roads. please can you advise where i go from here as i cannot afford to keep replacing my tyres and would like to know how i get compensation for this? i am unable to take a photo of the latest pot hole due to it being on a busy roundabout but the i can provide the location of it.
Posted anonymously at 12:49, Fri 12 December 2025
-
I have also just noticed that this was reported five days before the incident in my own car. Clearly the pot hole had not been addressed, despite causing damage to someone else’s car. Consequently, the damage to my car is due to this not being responded to quick enough. The incident happened on the 10th of December.
Posted anonymously at 12:53, Fri 12 December 2025
-
Investigation: Not Started (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 19:14, Fri 12 December 2025
-
Investigation: Not Started (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 19:43, Fri 12 December 2025
-
Investigation: Not Started (Defect Found), Defect Repair: Temporary Repair Completed - A permanent repair will be carried out in the next 28 days.
Posted by West Northamptonshire Council at 19:51, Fri 12 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: Temporary Repair Completed - A permanent repair will be carried out in the next 28 days. - Thank you for your enquiry. A qualified Highways Inspector has attended the location and carried out an immediate permanent repair. Your enquiry will now be closed. If for any reason you believe we have not attended the correct defect, please inform us by raising a new enquiry.
Posted by West Northamptonshire Council at 10:55, Mon 15 December 2025
Provide an update
Your information will only be used in accordance with our privacy policy