A number of potholes have appeared along this stretch of road. I counted at least 5 from the turning to the allotments right up to the first roundabout
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 05:24, Sat 6 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 12 days.
Posted by West Northamptonshire Council at 12:36, Mon 8 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 19:33, Wed 10 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled
State changed to: Investigating
Posted by West Northamptonshire Council at 13:55, Thu 18 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 08:07, Fri 19 December 2025
-
Damage is quite severe, I hit this and it burst my tyre
Posted anonymously at 17:18, Wed 24 December 2025
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled - Thank you for your enquiry. A qualified Highways Inspector has re-assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 2 repair. We will schedule a repair to be completed within 7 days.
Posted by West Northamptonshire Council at 08:23, Friday 2 January 2026
-
Still open, via questionnaire, 06:59, Saturday 3 January 2026
-
Numerous deep pot holes still present on this stretch of Northampton Road, both sides. Previous reports stated it will be resolved in 7 days. We are now 11 days in.
Posted anonymously at 17:10, Sunday
-
Investigation: Completed (Scheduled Maintenance), Defect Repair: Scheduled - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on 8508508 and add updates. The expected completion date for these works will be 14/01/26
Posted by West Northamptonshire Council at 20:46, Sunday
-
Investigation: Completed (Scheduled Maintenance), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 10:37, Wednesday
-
Investigation: Completed (Scheduled Maintenance), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 11:03, Wednesday
This report is now closed to updates from the public. You can make a new report in the same location.