Two large potholes Billing brook Rd jnc Fraser Rd

Reported via desktop in the Potholes / Highway Condition category anonymously at 10:26, Sun 7 December 2025

Sent to West Northamptonshire Council less than a minute later. ref: 8511906.

Two potholes repaired in past have reopened and are now getting bigger and deeper. Vehicles are driving in middle of road over speed humps to avoid them.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 10:27, Sun 7 December 2025

  • Photos of the pothole, you have to drive on the wrong side of the road to avoid them and 1 is big enough for your wheel to drop into

    Posted anonymously at 11:20, Mon 8 December 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.

    Posted by West Northamptonshire Council at 13:52, Mon 8 December 2025

  • Questionnaire filled in by problem reporter

    State changed to: Fixed

    Posted anonymously at 16:38, Monday 5 January 2026
    Still open, via questionnaire

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on FMS-8511906-1 and add updates. The expected completion date for these works will be 08/06/2026.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 08:11, Tuesday 6 January 2026

  • Investigation: Ongoing (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on FMS-8511906-1 and add updates. The expected completion date for these works will be 08/06/2026.

    Posted by West Northamptonshire Council at 08:54, Tuesday 6 January 2026

  • These holes are now dangerous and are much deeper than when reported.

    Posted by West Northamptonshire Council at 09:07, Thursday 15 January 2026

Provide an update

Your information will only be used in accordance with our privacy policy

Next: Tell us about you

Your update

Tell us about you

Do you have a West Northamptonshire Council FixMyStreet password?