Dangerous Pothole On Blind Corner

Reported via desktop in the Potholes / Highway Condition category anonymously at 16:19, Wed 17 December 2025

Sent to West Northamptonshire Council less than a minute later. ref: 8560797.

Pothole is on a blind corner which vehicles are swerve to avoid, meaning they are in the middle of the road on a blind bend. Several near misses.

Several previously failed fixes.

Updates

  • Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.

    State changed to: Investigating

    Posted by West Northamptonshire Council at 16:19, Wed 17 December 2025

  • Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 12 days.

    Posted by West Northamptonshire Council at 18:26, Fri 19 December 2025

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 09:50, Monday 12 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled

    State changed to: Investigating

    Posted by West Northamptonshire Council at 09:35, Wednesday 14 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 18:44, Wednesday 14 January 2026

  • Getting worse.

    Posted anonymously at 18:27, Friday 16 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 12 days.
    For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
    You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways

    Posted by West Northamptonshire Council at 08:51, Monday 19 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: To be Rescheduled

    State changed to: Investigating

    Posted by West Northamptonshire Council at 15:04, Monday 19 January 2026

  • Investigation: Completed (Defect Found), Defect Repair: Scheduled

    State changed to: Action scheduled

    Posted by West Northamptonshire Council at 14:21, Tuesday 20 January 2026

  • Right!

    This defect was originally reported on 17th December 2025 and was first inspected on 19th December and accepted as a priority 3 defect with a timeframe for repairs given as within 28 days and on average within 12 days.

    We are now on 31st January and the defects (multiple potholes on this sharp fast dangerous bend) not only remain but they are now incredibly large and deep and a serious threat to life.

    I can see on 19th January the defect was change to to be rescheduled but no explanation given as to why and then on 20th January an update stated the defect repair had been scheduled but with no timeframe given this time around.

    The defect(s) on this corner are now so severe that they are a priority 1 defect.... can you please advise of when a full permanent repair will be carried out and also provide a full thorough explanation of how the horrendous and unacceptable mismanagement of this FMS report has been allowed to occur.

    I will be bringing this up with the WNC Ward Councillors for Rural South Northamptonshire Ward along with Cllr Richard Butler and Cllr Mark Arnull and Sarah Bool MP.

    As part of an ongoing complaint into the horrendous condition and unacceptable maintenance of the roads I may well submit a FOI request against the specific FMS report asking which WNC employees and external contractors have been involved in its handling so that they can be held personally accountable

    YOU MUST DO BETTER WNC & WNH!!!

    Posted anonymously at 21:47, Saturday 31 January 2026

  • Investigation: Not Started (Defect Found), Defect Repair: Ongoing

    State changed to: In progress

    Posted by West Northamptonshire Council at 11:36, Monday 2 February 2026

  • Investigation: Not Started (Defect Found), Defect Repair: Work Completed

    State changed to: Fixed

    Posted by West Northamptonshire Council at 11:57, Monday 2 February 2026

  • Investigation: Completed (Work Completed), Defect Repair: Work Completed - Thank you for your enquiry. A qualified Highways Inspector has attended the location and carried out an immediate permanent repair. Your enquiry will now be closed. If for any reason you believe we have not attended the correct defect, please inform us by raising a new enquiry.

    Posted by West Northamptonshire Council at 12:30, Friday 6 February 2026

This report is now closed to updates from the public. You can make a new report in the same location.