Kett Road Pothole
Reported via iOS in the Potholes / Highway Condition category anonymously at 00:54, Wednesday 14 January 2026
Sent to West Northamptonshire Council less than a minute later. ref: 8683637.
Recent roadworks have left the road in a mess with damaged potholes
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 00:54, Wednesday 14 January 2026
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 4 repair. We will schedule a repair to be completed within 26 weeks. Our current average response time for a Priority 4 repair is 59 days.
Posted by West Northamptonshire Council at 10:50, Tuesday 20 January 2026
-
The pothole is becoming bigger and causing damage to my car - it’s like ditch / uneven.
Posted anonymously at 13:46, Tuesday 27 January 2026
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. We can confirm that we have been made aware of this issue. A works order has been raised which you can follow on FMS-8683637-1 and add updates. The expected completion date for these works will be 21/07/2026.
Posted by West Northamptonshire Council at 17:30, Friday 30 January 2026
-
The huge pothole on the junction of Chaucer street and kingsley park terrace is so dangerous multiple cars every day are being damaged by this pothole there is nearly accidents every day from people swerving to avoid it It currently measures 1.5mtr x 2.6mtr at its deepest it is 150mm an on average is 100mm deep it needs dealing with as a priority
Posted anonymously at 11:06, Monday 9 February 2026
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that we have already been made aware of this issue. A works order has been raised which you can follow on 8833136 and add updates. The expected completion date for these works will be 16/2/26.
Posted by West Northamptonshire Council at 13:50, Monday 9 February 2026
-
You’ve done a bodge job - kindly fix it properly!
Posted anonymously at 16:33, Tuesday 10 February 2026
-
How do we make an official complaint for the work that’s been completed? It’s disgusting how you guys get away with the poor work!!!
Posted anonymously at 16:34, Tuesday 10 February 2026
-
Road repairs are not done to a high standard this is why we need to report the issues week in week out for the same potholes! You guys are milking the tax payers and providing an awful service!!! Time for change - we the public have had enough of this mess!!!
Posted anonymously at 16:36, Tuesday 10 February 2026
-
Disgusting
Posted anonymously at 08:13, Wednesday 11 February 2026
Still open, via questionnaire -
Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that we have already been made aware of this issue and have made the area safe. A works order has been raised which you can follow on 8833136 and add updates. The expected completion date for these works will be 16/2/26.
West Northamptonshire Council is committed to maintaining safe and reliable roads, but it isn’t possible to repair every pothole immediately. The council must prioritise repairs based on available budget, workforce capacity, and the need to address the most safety critical defects first. All decisions are guided by the Highway Inspection Manual, which sets out how road defects are assessed and the timescales for repair. This ensures that resources are used responsibly and that the highest risk issues, such as those posing a danger to road users, are dealt with as quickly as possible while lower risk defects are scheduled appropriately within the limits of available funding.Posted by West Northamptonshire Council at 16:01, Tuesday 17 February 2026
-
POOR - how can we live like this??? We report issues and the work is done to a bare minimum standard. The hole is sinking again!!!
Posted anonymously at 00:33, Wednesday 18 February 2026
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - We can confirm that we have already been made aware of this issue and have made the area safe. A works order has been raised which you can follow on 8833136 and add updates. The expected completion date for these works will be 16/2/26.
West Northamptonshire Council is committed to maintaining safe and reliable roads, but it isn’t possible to repair every pothole immediately. The council must prioritise repairs based on available budget, workforce capacity, and the need to address the most safety critical defects first. All decisions are guided by the Highway Inspection Manual, which sets out how road defects are assessed and the timescales for repair. This ensures that resources are used responsibly and that the highest risk issues, such as those posing a danger to road users, are dealt with as quickly as possible while lower risk defects are scheduled appropriately within the limits of available funding.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 18:39, Wednesday 18 February 2026
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 10:19, Thursday 19 February 2026
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 09:02, Friday 20 February 2026
-
Investigation: Not Started (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 11:22, Friday 20 February 2026
-
Fix it properly and we wouldn’t need to report it again and again
State changed to: In progress
Posted anonymously at 11:25, Friday 20 February 2026
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed - We can confirm that we have already been made aware of this issue and have made the area safe. A works order has been raised which you can follow on 8833136 and add updates. The expected completion date for these works will be 16/2/26.
West Northamptonshire Council is committed to maintaining safe and reliable roads, but it isn’t possible to repair every pothole immediately. The council must prioritise repairs based on available budget, workforce capacity, and the need to address the most safety critical defects first. All decisions are guided by the Highway Inspection Manual, which sets out how road defects are assessed and the timescales for repair. This ensures that resources are used responsibly and that the highest risk issues, such as those posing a danger to road users, are dealt with as quickly as possible while lower risk defects are scheduled appropriately within the limits of available funding.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 12:15, Tuesday 3 March 2026
-
Need resurfacing
State changed to: Open
Posted anonymously at 17:03, Wednesday 11 March 2026
Still open, via questionnaire
Provide an update