Reported via desktop in the Potholes / Highway Condition category anonymously at 09:36, Sunday 18 January 2026
Sent to West Northamptonshire Council less than a minute later. ref: 8711809.
Deep pothole hit - surprised not to burst tyre
Updates
-
Thank you for reporting a fault. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
State changed to: Investigating
Posted by West Northamptonshire Council at 09:36, Sunday 18 January 2026
-
Investigation: Ongoing - Please accept our apologies for the delay in responding. Due to the recent adverse weather conditions, we have had to reprioritise certain tasks. This enquiry is now scheduled to be inspected during the week commencing 23rd January. Thank you for your patience and understanding.
Posted by West Northamptonshire Council at 16:04, Friday 23 January 2026
-
Pothole is now quite extensive as well as deeper due to the rain this week.
Posted anonymously at 21:38, Wednesday 28 January 2026
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by West Northamptonshire Council at 21:38, Wednesday 28 January 2026
-
P2 defect, please repair
Posted anonymously at 08:42, Thursday 29 January 2026
-
Investigation: Completed (Defect Found) - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 12 days.
Posted by West Northamptonshire Council at 13:51, Thursday 5 February 2026
-
Now over 100mm deep, please prioritize accordingly
Posted anonymously at 10:03, Wednesday 11 February 2026
-
Thank you for providing an update. Officers will now investigate the concerns and this may take up to 5 working days. If you believe that your concerns are urgent then please phone us.
Posted by West Northamptonshire Council at 10:03, Wednesday 11 February 2026
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 12 days.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 09:44, Monday 16 February 2026
-
I cracked my alloy via this pothole yesterday
Posted anonymously at 07:33, Thursday 19 February 2026
-
Investigation: Completed (Defect Found), Defect Repair: Not Started - Thank you for your enquiry. A qualified Highways Inspector has assessed the location and we can confirm that in accordance with the WNC Highways Inspection Manual, the defect meets the requirement for a Priority 3 repair. We will schedule a repair to be completed within 28 days. Our current average response time for a Priority 3 repair is 12 days.
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighways
For more information about our services, please visit https://www.westnorthants.gov.uk/ parking-roads-and-transport
You can also keep up to date on highways by following us on Facebook and Twitter @wnhighwaysPosted by West Northamptonshire Council at 10:15, Tuesday 24 February 2026
-
This pot hole is seriously affecting saftey of all road users. This needs to be re assessed before a serious injury or death occurs.
The pot hole is so big and deep cars now have to stop and give way to oncoming traffic.
Cars also have been seen to come into the farside of the road to avoid. This could result in a car accident.
This could cause an accident resulting in serious injury or death.
Posted anonymously at 18:04, Monday 9 March 2026
-
Investigation: Not Started (Defect Found), Defect Repair: Scheduled
State changed to: Action scheduled
Posted by West Northamptonshire Council at 10:02, Wednesday 11 March 2026
-
Investigation: Completed (Defect Found), Defect Repair: Scheduled - We can confirm that we have already been made aware of this issue and a works order has been raised on a routine safety inspection. The expected completion date for these works will be 16/3/26
Posted by West Northamptonshire Council at 07:54, Friday 13 March 2026
-
Investigation: Completed (Defect Found), Defect Repair: Ongoing
State changed to: In progress
Posted by West Northamptonshire Council at 08:45, Friday 13 March 2026
-
Investigation: Completed (Defect Found), Defect Repair: Work Completed
State changed to: Fixed
Posted by West Northamptonshire Council at 14:24, Tuesday 17 March 2026